Entergy Says Vermont Should Butt Out of Generator Review

NRC/Entergy Nuclear

The Vermont Yankee nuclear plant's owner is again trying to limit the state's regulatory authority over the Vernon reactor — this time over a new diesel-fired backup generator the plant intends to install.

Entergy Corp. argued Tuesday in federal court that the generator needs to be installed by September to meet Nuclear Regulatory Commission regulations. Company lawyers say they've asked for the state Public Service Board's OK, but add that the board has been dragging its feet.

Now Entergy is asking for a ruling from U.S. District Court Judge Christina Reiss  saying federal law pre-empts the state from having any say in the matter.

Meanwhile, the Public Service Board continues to review the matter.

Lawyers for the state say Entergy is exaggerating how fast the board needs to rule.

Copyright 2013 Associated Press. All Rights Reserved.