Vermont Yankee Says Shutdown To Cost $1.24 Billion

Your browser doesn’t support HTML5 audio

Vermont Yankee Nuclear Power Plant before decommissioning
Courtesy NRC and Entergy Corp.

The Vermont Yankee nuclear power plant has released a new estimate of what it will cost to decommission the reactor, manage high-level radioactive waste and restore the plant site.

The estimate of about $1.24 billion — is nearly double what plant owner Entergy Corp. currently has saved in the plant's decommissioning fund.

Vermont Yankee’s Martin Cohn says $368 million of the total is attributable to the need for the plant to manage its high-level radioactive waste. He says much of that cost is due to the failure of the U.S. Department of Energy to develop a long-awaited plan for removing highly radioactive spent fuel from commercial reactors around the country.

Vermont Yankee announced 14 months ago that it would close at the end of this year.